First project manager Kalle talks about hours.
Then Kalle speaks about project plan status. The plan
haven’t complete yet, it will be add more things.
Kalle shows the figure about relationship between malan
user interface and external programming, and malan code.
Jukka shows the new version of requirement analysis.
13:30
The Client Teemu comes to discuss more detail about requirement
and interface.
He gets one copy of requirement analysis and he will give the
comment by the beginning of the next week. Jukka will make
some changing according Teemu’s feedback.
We hope the requirement document can be ready by the next
meeting and the group can inspect the document.
14:00
Teemu leaves. The group continues to discuss.
Kalle talks again the project plan, it will update all the
time acconding the steps of project process.
Jianling talks about the testing process and testing level.
Kalle also explains some about them.
This is the simple starting. Antti gives some suggests on
the paper, Jianling will add more details information into
the document.
Alberto talks about design process. 15:15 Alberto leaves.
Kalle uses figure to analyse SWOT (Strengths, Weaknesses,
Opportunities and Threats).
We mainly deal with three phases: lack of feedback,
timetable and lack of process.
Kalle uses the computer to show the CVS
(Concurrent Versioning System) to the group.
The next group meeting will hold on the next
Thursday (12.02) between 12:00-16:00 because Kalle has
a trip. The Antti will reserve the classroom and inform
the group by e-mail.
The schedule of the next meeting is: make the
timetable done, state requirement, implementation process,
algorithm and so on.
Meeting ending: 16:10.
|