Date 13.4.2004 klo 14.00-16.00
Address Helsinki, TKT:n / C477
present Kärkkäinen Kalle Tapani (president)
Antti Tevanlinna (director)
Forsgren Jukka
Marquinez Alberto (secretary)
Sierla Sami Pekka
Zhang Jianling
absent
Malan implementation projects work review
and situation minutes.
Start meeting at 14.15
- Compiler module
Compiler module is ready for make process tests.
Kalle thinks that maybe have to make fey review modifies before start
with the official test process.
- Core module
Core module is almost ready. However some things
have to rebuild for elements of the source.
This module will be delayed two weeks before it is
ready to make any process test. Jukka thinks that
Core module is ready on 15.4.2004.
- UI module
First platform is almost ready. It has to be tested
before we will start our test process, in special
with some symbol table and options messages.
Others pieces are on working too.
This module must be ready on the 23.4.2004
to start test processes.
- Testing process plans start strategy.
The sources test processes will start on the 23.4.2004.
That is two weeks delayed.
Before that we have to get some integrates test ready.
On the 23.4.2004 shall start the really test process.
So all project module must be ready to move to the next situation.
Kalle repaired timetable, because all project are delayed fey weeks.
We have to regulate ours works resources because we don’t
Malan implementation projects work review and situation minutes.
have any more so much time.
Kalle checks that ours work time will get test process down.
Agenda for the next meeting:
- review all modules situation,
- start testing plan implementations work sharing
- review time table.
The meeting ends at 16.00
|