|
- The following table lists tasks, their duration and dependencies between them.
Compute the minimum duration for the project and determine the critical path.
Task | Duration days | predecessor |
---|
T1 | 10 | |
T2 | 15 | T1 |
T3 | 10 | T1,T2 |
T4 | 20 | |
T5 | 10 | |
T6 | 15 | T3,T4 |
T7 | 20 | T5 |
T8 | 35 | T7 |
T9 | 15 | T6 |
T10 | 5 | T5,T9 |
T11 | 10 | T9 |
T12 | 20 | T10 |
T13 | 35 | T3,T4 |
T14 | 10 | T8,T9 |
T15 | 20 | T12,T14 |
T16 | 10 | T15 |
- Draw a GANTT-diagram for the project of task 4.
If you want to use tools, MsProject 2000 is for use in class D326 (computers stubben 13-19)
Windows environment.
- Maintainability is considered as a software quality factor.
Find out its constituents (identify at least 7 constituents).
- CMM (Capability Maturity Model) classifies the software processes into five levels.
What are these levels and what are the main criteria for each level?
- The requirements for a software may be devided into fuctional (what the software is supposed to do)
and non-functional requirements.
Non-functional requirements may consider performance, security, usability, reliability,
maintainability, environment, etc. Last week's exercises had a task on
a system for handling registrations for studies.
Identify at least 7 non-functional requirements for this system and
analyse your requirements according to the criteria placed for well defined requirements.
|