Name
|
Start
|
End
|
Milestone
|
Progress
|
Assign To
|
Edit Notes...
|
| Aloitus | May 19, 2005 | May 24, 2005 | | 100 | Mikko, Kristian, Ilari, Hannu-Pekka, Tero, Allan |
|
| Projektisuunnitelman laatiminen | May 24, 2005 | May 27, 2005 | | 100 | Mikko, Kristian, Ilari, Hannu-Pekka, Tero, Allan |
|
| Projektisuunnitelma | May 27, 2005 | May 28, 2005 | * | 0 | |
|
| 1. Mittauspiste | May 31, 2005 | May 31, 2005 | * | 0 | |
|
| Vaatimusmäärittely | May 24, 2005 | Jun 17, 2005 | | 20 | |
|
| Vaatimusten kartoitus ja analysointi | May 24, 2005 | Jun 9, 2005 | | 60 | Ilari, Hannu-Pekka, Tero |
|
| Vaatimusten täsmennys | Jun 9, 2005 | Jun 14, 2005 | | 0 | Ilari, Hannu-Pekka, Tero |
|
| Vaatimusten validointi | Jun 14, 2005 | Jun 17, 2005 | | 0 | Ilari, Hannu-Pekka, Tero |
|
| Käyttöliittymäsuunnittelu | Jun 2, 2005 | Jun 17, 2005 | | 8 | |
|
| Skenaarioden selvittäminen | Jun 2, 2005 | Jun 8, 2005 | | 20 | Mikko, Kristian, Allan |
|
| Käyttötapausten laatiminen | Jun 8, 2005 | Jun 10, 2005 | | 0 | Mikko, Kristian, Allan |
|
| Käyttöliittymäprototyyppi | Jun 10, 2005 | Jun 17, 2005 | | 0 | Mikko, Kristian, Allan |
|
| Järjestelmätestien suunnittelu | Jun 15, 2005 | Jun 17, 2005 | | 0 | Hannu-Pekka, Allan |
|
| Valmiiden komponenttien valinta | Jun 15, 2005 | Jun 17, 2005 | | 0 | Kristian, Ilari |
|
| Määrittelydokumentti | Jun 17, 2005 | Jun 17, 2005 | * | 0 | |
|
| Käyttöliittymäproto | Jun 17, 2005 | Jun 17, 2005 | * | 0 | |
|
| 2. Mittauspiste | Jun 21, 2005 | Jun 22, 2005 | * | 0 | |
|
| Suunnittelu | Jun 20, 2005 | Jul 26, 2005 | | 0 | |
|
| Arkkitehtuurisuunnittelu | Jun 20, 2005 | Jun 22, 2005 | | 0 | Mikko, Kristian, Ilari, Hannu-Pekka, Tero, Allan |
|
| Abstrakti määrittely | Jun 22, 2005 | Jun 24, 2005 | | 0 | |
|
| Rajapintasuunnittelu | Jul 11, 2005 | Jul 15, 2005 | | 0 | |
|
| Komponettisuunnittelu | Jul 15, 2005 | Jul 20, 2005 | | 0 | |
|
| Tietorakennesuunnitelu | Jul 20, 2005 | Jul 26, 2005 | | 0 | |
|
| Integrointitestien suunnittelu | Jul 11, 2005 | Jul 15, 2005 | | 0 | |
|
| Muodollinen tarkastus | Jul 25, 2005 | Jul 26, 2005 | * | 0 | |
|
| Suunnitteludokumentti | Jul 26, 2005 | Jul 27, 2005 | * | 0 | |
|
| 3. Mittauspiste | Jul 29, 2005 | Jul 30, 2005 | * | 0 | |
|
| Toteutus | Jul 27, 2005 | Aug 16, 2005 | | 0 | |
|
| Toimiva sovellus | Aug 16, 2005 | Aug 17, 2005 | * | 0 | |
|
| 4. Mittauspiste | Aug 19, 2005 | Aug 20, 2005 | * | 0 | |
|
| Testaus | Jul 27, 2005 | Aug 26, 2005 | | 0 | |
|
| Yksikkötestaus | Jul 27, 2005 | Aug 12, 2005 | | 0 | |
|
| Integrointitestaus | Aug 12, 2005 | Aug 16, 2005 | | 0 | |
|
| Järjestelmätestaus | Aug 16, 2005 | Aug 26, 2005 | | 0 | |
|
| Testausraportti | Aug 26, 2005 | Aug 26, 2005 | * | 0 | |
|
| Käyttöohjeen laatiminen | Aug 16, 2005 | Aug 26, 2005 | | 0 | |
|
| Käyttöohje | Aug 26, 2005 | Aug 26, 2005 | * | 0 | |
|
| 5. Mittauspiste | Aug 30, 2005 | Aug 31, 2005 | * | 0 | |
|
| Viimeistely palautusta varten | Aug 29, 2005 | Sep 2, 2005 | | 0 | |
|
| Palautus | Sep 2, 2005 | Sep 2, 2005 | * | 0 | |
|
| Loma | Jun 24, 2005 | Jul 11, 2005 | | 0 | |
|